2013-12-03 - 6474 - SNC PROJECT - Daily Activity Log #SNCProject

SPECIFICATIONS

6474.200 - SNC PROJECT


Purpose


SNC PROJECT - Daily activities

Admin Info


Purpose
SNC PROJECT - daily activitie
Requested By
BMS
Spec Created By
Vengal Rao
Spec Created Date
12/03/2013
Spec QA by
vengal rao
Objects

Document Status
complete

References


Prior Tickets



Documents




Functional Requirement


The snc project daily activities documentation
The SNC Project consists of following activities.
1. Configuration of vendor confirmation key
2. Configuration for PO type to get Z3NB PO
3. Configuration to generate ASN to Customer
4. PO extract program
5. Inbound delivery and update SOLD TO as partner
6. Packing program
7. UCC label Printing
8. Putaway and PGR
9.ASN to customer
10. Invoice
11, SNC activity



Solution Summary


[Discuss this section with Requester and get approval prior to beginning work]
The snc project daily activities documentation

Daily activities


Item

Requirment category
details
requestor
last update upto























































Activity Log


Requirment
Details of Requirement
Req by
Req Dt
Activity
Spec
BMS
Date
Status
1. Confirmation key
For China plant , change the confiramtion
key details from ZNEC to ZSNC and add new confirmation
key ZQ
NEC
12/02
Created new key ZQ and added the
same in ZSNC -

VENGAL
12/02
completd
1 Confirmation Key
For China plant 9010 in the SD - shipping config change
the confirmation for NB and Z3NB from ZNEC to ZSNC

12/03
changed in spro in LE>SHIPPING>DELIVERIES
>DEFINE ORDER CONFIRMATIONS FOR INBOUND
DELIVERIES >for category F , PLANT - 9010 for NB and
Z3NB changed from ZNEC to ZSNC

vengal
12/02
completed
5. Inbound delivery
Discuss with tech team to add selection option for vendor and
confirmation key and also add validation in program

12/03
Infomed venkat to add Vendor and Confirmation Key as
selection option in the program and added validation - If ZT
already exists in the PO then ignore the PO as it will be a
DSSCO PO.

vengal
12/03
WIP
5. Inbound Delivery testing
Inbound Delivery is to be created specific to the sales order when sewing confirmations are update in the purchase order

12/03
Carried out testing with different Purchase orders

Aditya
12/05
WIP
Test Data to SAP
Test data (Material) given to SAP with prepack as unit of measure

12/03
test data to SAOP

Aditya
12/05
WIP
Extension of IDOC
Extension on the IDOC type to get 3 additional fields

12/05
gathered information on extension of IDOC and informed technical team about the fields to be added in the idoc

Aditya
12/05
WIP
5. Inbound delivery testing
Changes to program for QT Orders .
For QT orders, deliveries should be created within x days of status = confirmed. X should be set up as a selection option (default = 21 days)
-- Quick time order days should be calculated as :
Ex-factory date – PO creation days
NEC
12/04
Removed confirmation key ZQ from confirmation sequence ot ZSNC
and informed Sandeep the details of the program change for
Inbound delivery.

vengal
12/04
wip



















Test Plan

[List test scenarios/cases to be executed here]

Solution Details


[Provide complete technical details for configuration or programming here]

Issues